Construction of JNV School Complex at Durgapur. - 2006

Construction of JNV School Complex at Durgapur. - 2006

Project Image 1 Project Image 2 Project Image 3 Project Image 4
❮ ❯
Project Image 1 Project Image 2 Project Image 3 Project Image 4
❮ ❯


Client : Jawahar Navodaya Vidyalaya, Samiti, Ministry of HRD, Govt. of India..  Project : Construction of JNV School Complex at Durgapur.  Start Date :

Project Profile : Construction of JNV School Complex including Hostel, Residential Quarters including plumbing, sanitary, electrification, Overhead Tank, Roads, Sub-Station etc. at Durgapur.

Hiring of HEMM / Tippers for removal of overburden... - 2002

Hiring of HEMM / Tippers for removal of overburden... - 2002

Project Image 1 Project Image 2 Project Image 3 Project Image 4 Project Image 5
❮ ❯
Project Image 1 Project Image 2 Project Image 3 Project Image 4 Project Image 5
❮ ❯


Client : Western Coalfields Limited.  Project : Hiring of HEMM / Tippers for removal of overburden...  Start Date : 23-01-2002

Project Profile : Excavation and removal of 5.5 mill cu m of OB Soil with HEMM for Umrer open cast mine.

Manufacturing, Supplying and Laying of Pipeline with Ground Reservoir for Singrauli. - 2001

Manufacturing, Supplying and Laying of Pipeline with Ground Reservoir for Singrauli. - 2001

Project Image 1 Project Image 2 Project Image 3
❮ ❯
Project Image 1 Project Image 2 Project Image 3
❮ ❯


Client : Northern Coalfields Limited, Singrauli.  Project : Manufacturing, Supplying and Laying of Pipeline with Ground Reservoir for Singrauli.  Start Date : 19-11-2001

Project Profile : Manufacturing, Supplying and Laying of 1000 mm diameter Pipeline, length 700 mtr. from NTPC Pump House to Pipeline at IWSS of NCL. 300 mm diameter Pipeline of 6.70 Km length with 12,00,000 gallon capacity RCC Ground Reservoir for augmentation of Industrial Water Supply Arrangement from Chilkatand Reservoir to Light Vehicle Reservoir and onwards to Mine at Khadia OCP on a turnkey basis.

Manufacturing, Supplying and Laying of Pipeline with Ground Reservoir for Singrauli. - 1999

Manufacturing, Supplying and Laying of Pipeline with Ground Reservoir for Singrauli. - 1999

Project Image 1
Project Image 1


Client : Northern Coalfields Limited, Singrauli.  Project : Manufacturing, Supplying and Laying of Pipeline with Ground Reservoir for Singrauli.  Start Date :

Project Profile : Manufacturing, Supplying and Laying of 500 mm dia Pipeline of length 11.5 Km, 400 mm dia of length 3.5 Km and 250 mm dia of length 2.5 Km with 6.3 lakh gallon capacity RCC Ground Reservoir near Kakri Hill, 3.5 lakh gallon capacity RCC Ground Reservoir at Jhingurdah and 2.0 lakh gallon capacity RCC Ground Reservoir at Singrauli for linking of water supply arrangement from IWSS to Jhingurdah and NCL Hq., Singrauli on a turnkey basis.

Manufacturing, Supplying and Laying of Pipeline for Upgradation of water supply arrangement for Kakri. - 1998

Manufacturing, Supplying and Laying of Pipeline for Upgradation of water supply arrangement for Kakri. - 1998

Project Image 1 Project Image 2 Project Image 3
❮ ❯
Project Image 1 Project Image 2 Project Image 3
❮ ❯


Client : Northern Coalfields Limited, Singrauli.  Project : Manufacturing, Supplying and Laying of Pipeline for Upgradation of water supply arrangement for Kakri.  Start Date : 12-05-1998

Project Profile : Manufacturing, Supplying and Laying of 300 mm dia Pipeline of 1.5 Km length for up-gradation of water supply arrangement from Kakri Industrial Off-take along PWD Road to underground tank in front of GM office on a turnkey basis.

Manufacturing, Supplying and Laying of Pipeline with Ground Reservoir for Singrauli. - 1998

Manufacturing, Supplying and Laying of Pipeline with Ground Reservoir for Singrauli. - 1998

Project Image 1 Project Image 2 Project Image 3 Project Image 4
❮ ❯
Project Image 1 Project Image 2 Project Image 3 Project Image 4
❮ ❯


Client : Northern Coalfields Limited, Singrauli.  Project : Manufacturing, Supplying and Laying of Pipeline with Ground Reservoir for Singrauli.  Start Date : 11-05-1998

Project Profile : Manufacturing, Supplying and Laying of 250 mm dia Pipeline of 10.5 Km length with Ground Reservoir of 1000 Cu.m. capacity for linking of water supply arrangement from Singrauli to Gorbi on a turnkey basis.

Manufacturing, Supplying and Laying of New Pipeline and Rehabilitation of OId Pipelines for IWSS of NCL. - 1998

Manufacturing, Supplying and Laying of New Pipeline and Rehabilitation of OId Pipelines for IWSS of NCL. - 1998

Project Image 1 Project Image 2 Project Image 3 Project Image 4 Project Image 5
❮ ❯
Project Image 1 Project Image 2 Project Image 3 Project Image 4 Project Image 5
❮ ❯


Client : Northern Coalfields Limited, Singrauli.  Project : Manufacturing, Supplying and Laying of New Pipeline and Rehabilitation of OId Pipelines for IWSS of NCL.  Start Date : 12-05-1998

Project Profile : Manufacturing, supplying and Laying of 1000 mm diameter New Pipeline and Rehabilitation of 914 mm, 614 mm & 415 mm diameter Old Pipelines with lining and guniting total length 28 Km for the Integrated Water Supply Scheme (IWSS) of NCL feeding Bina, Kakri, Khadia, Dudhichua, CWS, Jayant, Nigahi mines / township on a turnkey basis.

Construction of Extension of Haul Road for Main and West Midentry, Dudhichua. - 1997

Construction of Extension of Haul Road for Main and West Midentry, Dudhichua. - 1997

Project Image 1
Project Image 1


Client : Northern Coalfields Limited, Singrauli.  Project : Construction of Extension of Haul Road for Main and West Midentry, Dudhichua.  Start Date : 28-04-1997

Project Profile : Construction of Extension of Haul Road for Main and West Midentry including drain and retaining wall etc. at Dudhichua.

Construction of Haul Road for Dudhichua project. - 1997

Construction of Haul Road for Dudhichua project. - 1997

Project Image 1
Project Image 1


Client : Northern Coalfields Limited, Singrauli.  Project : Construction of Haul Road for Dudhichua project.  Start Date : 28-04-1997

Project Profile : Construction of Haul Road at Midentry at Western Section Dudhichua Project.

Construction of Haul Road for Khadia project. - 1996

Construction of Haul Road for Khadia project. - 1996

Project Image 1 Project Image 2 Project Image 3
❮ ❯
Project Image 1 Project Image 2 Project Image 3
❮ ❯


Client : Northern Coalfields Limited, Singrauli.  Project : Construction of Haul Road for Khadia project.  Start Date : 28-04-1996

Project Profile : Construction of Haul Road, Light Vehicle Road, Side drain, Toe wall etc. in Midentry at Khadia.

Water Treatment Plant for Lakhanpur Group of Mines. - 1995

Water Treatment Plant for Lakhanpur Group of Mines. - 1995

Project Image 1
Project Image 1


Client : Mahanadi Coalfields Limited, Sambalpur.  Project : Water Treatment Plant for Lakhanpur Group of Mines.  Start Date : 18-02-1995

Project Profile : Construction of Water Treatment Plant of 7.26 MLD capacity for IWSS Lakhanpur Group of Mines at Ib Valley Area on a turnkey basis..

Widening of Haul Road for Khadia project. - 1995

Widening of Haul Road for Khadia project. - 1995

Project Image 1 Project Image 2
❮ ❯
Project Image 1 Project Image 2
❮ ❯


Client : Northern Coalfields Limited, Singrauli.  Project : Widening of Haul Road for Khadia project.  Start Date : 15-07-1995

Project Profile : Construction of Widening of Haul Road including protection work at Khadia Project.

Construction of Haul Road for Amlohri project. - 1992

Construction of Haul Road for Amlohri project. - 1992

Project Image 1 Project Image 2 Project Image 3 Project Image 4
❮ ❯
Project Image 1 Project Image 2 Project Image 3 Project Image 4
❮ ❯


Client : Northern Coalfields Limited, Singrauli.  Project : Construction of Haul Road for Amlohri project.  Start Date : 25-02-1992

Project Profile : Construction of Haul Road at Amlohri Project.

Ground Water Reservoir for Bharatpur OCM, Talcher Area. -

Ground Water Reservoir for Bharatpur OCM, Talcher Area. -

Project Image 1 Project Image 2
❮ ❯
Project Image 1 Project Image 2
❮ ❯


Client : Central Coalfields Limited..  Project : Ground Water Reservoir for Bharatpur OCM, Talcher Area.  Start Date :

Project Profile : Design and Construction of Ground water bulk reservoir for IWSS of Talcher Area.

Construction of G+4 Residential Building, for Paikpara. -

Construction of G+4 Residential Building, for Paikpara. -

Project Image 1 Project Image 2 Project Image 3
❮ ❯
Project Image 1 Project Image 2 Project Image 3
❮ ❯


Client : Shakti Development Pvt. Ltd., Kolkata..  Project : Construction of G+4 Residential Building, for Paikpara.  Start Date :

Project Profile : Construction of G+4 Residential Building at Paikpara, Kolkata, on turnkey basis.